Quick answer: A Los Angeles construction project has three phases — design and planning (4–12 weeks), permitting (3–14 weeks depending on project type and city), and construction itself — with LADBS permitting alone often taking as long as the design phase before any work begins. APLA Construction (CA Lic #1136359) provides a written project schedule before any work begins.
One of the most common questions homeowners ask before starting a construction project in Los Angeles is “how long will this actually take?” The answer is significantly different in LA than in most other California cities — primarily because the Los Angeles Department of Building and Safety (LADBS) adds permitting time that can run 6–14 weeks before construction even begins. This guide breaks down realistic construction timelines for every major project type in 2026. APLA Construction (CA Lic #1136359) has completed hundreds of projects across Los Angeles and the greater metro area.
A Los Angeles construction timeline has three phases:
Total project duration = Phase 1 + Phase 2 + Phase 3. The key insight: in LA, permitting often takes as long as construction for smaller projects.
| Project Type | Standard Plan Check | Expedited (add $1,500–$4,000) |
|---|---|---|
| Kitchen remodel (plumbing/electrical only) | 4–8 weeks | 2–3 weeks |
| Bathroom remodel | 4–8 weeks | 2–3 weeks |
| ADU (garage conversion) | 6–10 weeks | 3–4 weeks |
| ADU (new detached) | 8–14 weeks | 4–6 weeks |
| Room addition (ground floor) | 8–14 weeks | 4–6 weeks |
| Second story addition | 10–16 weeks | 5–8 weeks |
| New home construction | 14–22 weeks | 7–12 weeks |
If your property is in an independent city rather than the City of Los Angeles, permit timelines are typically significantly faster:
With permits (as all mid-range and above renovations should have): 14–20 weeks for a mid-range renovation, 18–28 weeks for a high-end or structural renovation. LADBS plan check (4–8 weeks) runs concurrently with material ordering, so the permitting time does not always add directly to construction time.
Garage conversion: 14–22 weeks total. New detached ADU: 22–38 weeks total. The ADU-specific permit process (LADBS ADU plan check) is currently 6–14 weeks depending on the complexity. APLA submits ADU applications strategically to minimize LADBS review time.
32–50 weeks total from project start to move-in. Plan check is 10–16 weeks. Construction is 16–28 weeks for the structural work, rough-in trades, and finishes. Second story additions are the longest residential renovation projects because of the structural complexity and the full LADBS review required.
Yes. APLA (CA Lic #1136359) provides a detailed project schedule with every proposal — showing design, permitting, material lead time, and construction phases. Call (818) 818-4419 for a free consultation and project timeline assessment.
Call: (818) 818-4419
Email: info@aplaconstruction.com
CA General Contractor License #1136359 — verify on CSLB
General Contractor Los Angeles | ADU Construction LA | Room Additions LA | Home Remodeling LA